1. 9th October; Land purchase (donated). 2. 1st December 2021- 30th January 2022 obtains land documents. 3. 1st December 2021 – 5th December site clearance. 4. 20th December 2021 – 30th January: architectural drawings. 5. 1st December 2021- 30th January 2022: retaining wall and material filling to elevate the entire land to a suitable level. 6. 1st February 2022- 2nd March: building Sub structure. 7. 3rd March 2022- 23rd March 2022: ground floor concrete works. 8. 25th March 2022- 19th April 2022: clay brick columns formation. 9. 15th April 2022- 20th June 2022: superstructure works for first floor (reinforcement, formwork, concrete works). 10. 22nd June 2022- 30th August: clay brick double walls. 11. 1st August 2022- 30th August 2022: windows and doors Fabrication. 12. 1st September 2022- 30th September 2022: wall partitioning. 13. 4th September 2022- 15th October 2022: Roof steel structure Fabrication and roof installation. 14. 18th April 2022- 4th September 2022: External works (car park floor pavement works, security Fence, 2 entrance Gates). 15. 22nd July 2022- 30th August 2022: water tank and mechanical room stand (steel structure). 16. 1st October 2022- 30th October 2022: glass wall cladding installation, doors and windows installation. 17. 1st October 2022- 30th October 2022: electrical, Mechanical and plumbing works. 18. 2nd November 2022- 30th November 2022: finishing works (lights installation, sanitary wear installation, Air-conditioning installation, painting works). 19. 1st December 2022- 8th December 2022: final inspection and furniture installation. 20. 10th December: handing over and opening ceremony.