Bellow is the brief of the Project Schedule for the Construction

1. 9th October; Land purchase (donated).
2. 1st December 2021- 30th January 2022 obtains land documents.
3. 1st December 2021 – 5th December site clearance.
4. 20th December 2021 – 30th January: architectural drawings.
5. 1st December  2021- 30th January  2022: retaining wall and material filling to elevate the entire land to a suitable level.
6. 1st February  2022- 2nd March: building Sub structure.
7. 3rd March 2022- 23rd March 2022:  ground floor concrete works.
8. 25th March 2022- 19th April 2022: clay brick columns formation.
9. 15th April 2022- 20th June 2022: superstructure works for first floor (reinforcement, formwork, concrete works).
10. 22nd June 2022- 30th August: clay brick double walls.
11. 1st August 2022- 30th August 2022: windows and doors Fabrication.
12. 1st September 2022- 30th September 2022: wall partitioning.
13. 4th September 2022- 15th October 2022: Roof steel structure Fabrication and roof installation.
14. 18th April 2022- 4th  September 2022: External works (car park floor pavement works, security Fence, 2 entrance Gates).
15. 22nd July 2022- 30th August 2022: water tank and mechanical room stand (steel structure).
16. 1st October 2022- 30th October 2022: glass wall cladding installation, doors and windows installation.
17. 1st October 2022- 30th October 2022: electrical, Mechanical and plumbing works.
18. 2nd November 2022- 30th November 2022: finishing works (lights installation, sanitary wear installation, Air-conditioning installation, painting works).
19. 1st December 2022- 8th December 2022: final inspection and furniture installation.
20. 10th December: handing over and opening ceremony.

BUILDING UPDATE 1

Construction of the new NCEH building started 2 months ago. Now we are ….

BUILDING UPDATE 2

Fence is almost completed and main Construction will begin soon…

BUILDING UPDATE 3

Leveling and compacting of the land right after the Construction of the wall..

BUILDING UPDATE 4

Foundation for building completed. Timeline delayed due to the rains.

BUILDING UPDATE 5

In mid-November the construction of NCEH was resumed. We hope to finish with the walls by the end of this year.

BUILDING UPDATE 6

It’s exciting to see the structure taking shape and we can’t wait for the finished product. Follow us for updates as the construction continues.

BUILDING UPDATE 7

Is been a great journey. Thanks to you our donors and partners, we are getting there.

BUILDING UPDATE 8

The second floor was already decked so we are building the third floor.

BUILDING UPDATE 9

The 2nd floor of our eye hospital is being constructed.

BUILDING UPDATE 10

The completion of the second-floor construction marks the beginning of roof installation. The roof design will be concealed.

BUILDING UPDATE 11

The new Northern Community Eye Hospital building has finally been roofed, and plastering work is currently underway.

BUILDING UPDATE 12

The plastering of both the exterior and interior surfaces of the New NCEH building has been successfully completed. This marks a significant milestone in the construction process, bringing the project closer to its final stages of completion.